I-35 Road Resurfacing Project

Harris, Rush City

Traffic impacts

project location map
I-35 Chisago/Pine County line to Harris project location map
Click map for larger PDF version
.

Upcoming

Specific information on traffic impacts will be provided as more details become available.

Future

  • I-35 will be restricted to a single lane of traffic in each direction
  • Access at Rush City will be maintained with a short-term closure to reconstruct ramps

About this project

A more than eight-mile section of I-35 between the city of Harris and the Chisago/Pine County line will undergo a concrete road resurfacing project. The work will include concrete pavement work, drainage updates and safety improvements. This section of I-35 was first paved in 1969. The road received pavement overlay treatments in 1987 and 2008.

Summary of work

  • Resurface concrete pavement
  • Remove and replace cable median barriers
  • Add rumble strips
  • Update drainage
  • Replace lighting at Rush City interchange

Preliminary Construction Schedule

Fall 2018: Construct temporary crossovers and emergency pulloffs
March - June 2019: Construct SB lanes with all traffic on NB
       June 2019: SB Rush City ramps will close for 2-4 weeks
July 2019 – October 2019: Construct NB lanes with all traffic on SB
       Sept. 2019 – NB Rush City ramps will close for 2-4 weeks
Project Completion Date: Late October 2019