Oct. 6, 2017

Major traffic changes begin today on Ramsey County Road I in Arden Hills and Shoreview

ROSEVILLE, Minn. – With completion of work on the south side of Ramsey County Road I near Rice Creek Parkway and Old Highway 8, you’ll find major traffic changes in the area beginning today. County Road I traffic is now a single lane in each direction on the south side of the road east of I-35W.

Additional traffic changes include:

  • County Road I is closed at I-35W between the ramps on each side of the interstate.
    Note: The ramps between southbound I-35W and County Road I on the west side of the interstate remain open. The ramp from northbound I-35W to County Road I is closed until December.
  • Rice Creek Parkway is closed at County Road I. You will have to follow a signed detour to reach Rice Creek Parkway.
  • The new Old Hwy 8 frontage road is now open between County Rd I and County Road H on the east side of I-35W. County Road I traffic on the east side of the interstate will detour south on the new frontage road to reach northbound and southbound I-35W and to reach County Road I west of the interstate.
  • I-35W traffic will use County Road H and the new Old Hwy 8 frontage road to reach County Road I east of I-35W as well as the Drivers’ Exam Station and Minnesota Fleet & Surplus Services locations. The new ramp from northbound I-35W to County Road H opened in mid-September.

The Ramsey County project includes construction of a roundabout at the ramp from I-35W northbound, Rice Creek Parkway and Old Highway 8 which leads in to the Arden Hills Driver Services facility. The county is also rebuilding and realigning the ramp from northbound I-35W to County Road I. The ramp from County Road I to northbound I-35W has closed permanently.

In addition, the county plans to improve trail access, build raised medians and new road shoulders. The newly opened frontage road between County Road H and County Road I on the east side of the freeway is also part of the work.

Weather permitting, the project is expected to be complete by early December.

For more information, please visit the project web site:  https://www.ramseycounty.us/residents/roads-transit/2017-construction-maintenance/county-road-irice-creek-parkway-roundabout.

For more information on the benefits of roundabouts and how to drive them, check out MnDOT’s roundabout website. For updated road condition information, call 511 or visit www.511mn.org.

###